SaveOptions.RollUpGanttBars
Contents
[
Hide
]SaveOptions.RollUpGanttBars property
Gets or sets a value indicating whether subtasks on the summary task bar should be marked. For subtasks, the Rollup field indicates whether information on the subtask Gantt bars will be rolled up to the summary task bar. For summary tasks, the Rollup field indicates whether the summary task bar displays rolled up bars. You must have the Rollup field for summary tasks set to Yes for any subtasks to roll up to them.
public bool RollUpGanttBars { get; set; }
Remarks
Is only applicable when Gantt chart view is rendered.
Examples
Shows how to set a value indicating that subtasks on the summary task bar must be rolled up.
var project = new Project(DataDir + "Project2.mpp");
project.DisplayOptions.ShowProjectSummaryTask = true;
project.Set(Prj.ShowProjectSummaryTask, true);
var options = new PdfSaveOptions
{
PresentationFormat = PresentationFormat.GanttChart,
FitContent = true,
RollUpGanttBars = true,
// OR
// options.RollUpGanttBars = false;
// DrawNonWorkingTime = true,
PageSize = PageSize.A3
};
project.Save(OutDir + "RenderGanttChartWithBarsRolledUp_out.pdf", options);