]GanttChartView.BottomTimescaleTier property
Gets or sets settings of view’s bottom timescale tier. TimescaleTier
public TimescaleTier BottomTimescaleTier { get; set; }
Examples
Shows how to work with timescale tiers through save options.
var project = new Project(DataDir + "CreateProject2.mpp");
GanttChartView ganttChartView = (GanttChartView) project.Views.ToList()[0];
// set the timescale tiers of the Gantt Chart view
ganttChartView.MiddleTimescaleTier.Unit = TimescaleUnit.Months;
ganttChartView.MiddleTimescaleTier.Count = 1;
ganttChartView.MiddleTimescaleTier.Label = DateLabel.MonthMmmm;
ganttChartView.BottomTimescaleTier.Unit = TimescaleUnit.Days;
ganttChartView.BottomTimescaleTier.Count = 1;
ganttChartView.BottomTimescaleTier.Label = DateLabel.DayDddDd;
// ...
var options = new ImageSaveOptions(SaveFileFormat.Png)
{
Timescale = Timescale.DefinedInView
};
// ...
// save the project as an image
project.Save(OutDir + "WorkWithTimescaleTier_out.png", options);
Shows how to modify timescale tiers.
var project = new Project();
// Init Gantt Chart View
var view = new GanttChartView
{
TopTimescaleTier = new TimescaleTier(),
MiddleTimescaleTier = new TimescaleTier(),
BottomTimescaleTier = new TimescaleTier()
};
// set Time Scale count
view.TopTimescaleTier.Count = 2;
view.TopTimescaleTier.Unit = TimescaleUnit.Quarters;
view.TopTimescaleTier.Label = DateLabel.QuarterQQyy;
view.TopTimescaleTier.ShowTicks = false;
view.MiddleTimescaleTier.Count = 2;
view.MiddleTimescaleTier.Unit = TimescaleUnit.Weeks;
view.MiddleTimescaleTier.Label = DateLabel.WeekDddDd;
view.MiddleTimescaleTier.ShowTicks = false;
view.BottomTimescaleTier.Unit = TimescaleUnit.Days;
view.BottomTimescaleTier.Label = DateLabel.DayDdd;
view.BottomTimescaleTier.Count = 2;
view.BottomTimescaleTier.ShowTicks = false;
// add Gantt Chart View to project
project.Views.Add(view);
// add some test data to project
var task1 = project.RootTask.Children.Add("Task 1");
var task2 = project.RootTask.Children.Add("Task 2");
task1.Set(Tsk.Duration, task1.ParentProject.GetDuration(24, TimeUnitType.Hour));
task2.Set(Tsk.Duration, task1.ParentProject.GetDuration(40, TimeUnitType.Hour));
// Use 'Timescale.DefinedInView' option to render timescales using timescale settings which we have set (view.TopTimescaleTier, view.MiddleTimescaleTier, view.BottomTimescaleTier).
var pdfSaveOptions = new PdfSaveOptions
{
Timescale = Timescale.DefinedInView,
StartDate = DateTime.Now.AddDays(-30),
EndDate = DateTime.Now.AddDays(30)
};
project.Save(OutDir + "WorkWithTimescaleTier_out.pdf", pdfSaveOptions);